The construction of the concrete towers at the Lokeren the construction site has been partially completed.

The construction of the concrete towers has been completed.

21/12/16

The construction of the concrete part of the wind turbine towers has been completed at our Lokeren site. A crane with a height of about 100 meters stacked concrete rings to a height of 80 meters.

A steel section of 20 meters will be placed on top of the concrete towers. The towers will then reach their full height of 100 meters.

The towers will be finished in the course of January.

Take a look at some impressive drone pictures of towers below.

Share on:
(images: Picarus)
(images: Picarus)
(images: Picarus)
(images: Picarus)
(images: Picarus)
No items found.
Operational
Under construction
In development

Into the wind farm
Lokeren

The Storm wind farm Lokeren consists of four wind turbines and is located north of the E17 highway near the town of Heiende (province of East Flanders).

Follow us on social media!

Ask us a question

Thanks!
Your form has been sent successfully.
We will contact you as soon as possible.
Something went wrong while submitting the form.