Construction site Courrière almost ready to build turbines.
13/1/23
On the site of Storm wind farm Courrière we continued working on the foundation of the three wind turbines. Before the holidays the foundation was filled with concrete. During the Christmas vacations, the site was closed and the concrete had all the time it needed to harden. It takes about 4 weeks for the concrete to dry completely, then the formwork is removed and the foundation is finished.
In February we expect the first parts on site, after that the construction of the turbines can start