The first wind turbine in Zoersel is in place.
27/10/21
The first wind turbine has been completed in Zoersel for a few days now. Due to the stormy weather last week, the work was temporarily halted. To be able to accomplish hoisting works, the wind must be nearly calm. Friday evening, the mast was entirely in place and on Saturday, the rotor was lifted and mounted.
Now the work moves to the site of the second wind turbine. This wind turbine will also be completed shortly.
The wind farm will be fully operational by the end of this year.