Start of the works on the fourth wind turbine in Meer.
We are busily working on our fourth wind turbine on the sites of company Malve on the industrial estate of Meirberg in Meer. To the north of the site, three wind turbines have been working to produce green energy to the full since 2015. As from this autumn, this additional turbine will produce sufficient energy to provide approximately 3,200 families with their annual energy consumption.
The piles for the foundation of this wind turbine were planted in the ground just before the end of last year. The construction pit has been made during the past few days, as you can see on the photographs. The reinforcement for the foundations will be constructed during the next phase. After that, the encasing will be filled with concrete and the foundation will be finished after a long period of hardening.